Each and every time it wil EUE at step 22. Each time the same
Code: Select all
[06:48:27] Completed 55000 out of 250000 steps (22 percent)
[07:25:42] Warning: long 1-4 interactions
[07:25:42] Gromacs cannot continue further.
[07:25:42] Going to send back what have done.
[07:25:42] logfile size: 51689
[07:25:42] - Writing 52225 bytes of core data to disk...
[07:25:42] ... Done.
[07:27:42]
[07:27:42] Folding@home Core Shutdown: EARLY_UNIT_END
[07:27:42]
[07:27:42] Folding@home Core Shutdown: EARLY_UNIT_END
[07:27:45] CoreStatus = 7B (123)
[07:27:45] Client-core communications error: ERROR 0x7b
[07:27:45] Deleting current work unit & continuing...
Intermixed with those EUEs I also got SIX of P3064 R3 C49 G81
Each and every one of those ended in an EUE like this
Code: Select all
[17:20:09] Completed 1050000 out of 5000000 steps (21 percent)
[17:41:16] Gromacs cannot continue further.
[17:41:16] Going to send back what have done.
[17:41:16] logfile size: 36011
[17:41:16] - Writing 36547 bytes of core data to disk...
[17:41:16] ... Done.
[17:41:16] - Failed to delete work/wudata_07.sas
[17:41:16] - Failed to delete work/wudata_07.goe
[17:41:16] Warning: check for stray files
[17:41:16]
[17:41:16] Folding@home Core Shutdown: EARLY_UNIT_END
[17:41:16]
[17:41:16] Folding@home Core Shutdown: EARLY_UNIT_END
[17:41:20] CoreStatus = 7B (123)
[17:41:20] Client-core communications error: ERROR 0x7b
[17:41:20] - Attempting to download new core...
[17:41:20] + Downloading new core: FahCore_a1.exe
Can you please figure out why these work units are so unstable and why, in one case, I was issued the P2665 R3 C815 G22 work unit FOUR times in a row, followed by the equally unstable P3064 R3 C49 G81 once - then another THREE of the P2665 R3 C815 G22. Your server should not be sending the same work unit to the same computer TWELVE times.